Dashboard · live from PLAN + Activity Log
Delivery Overview
25%
PLAN completato
2 di 8 task
50%
Activity Log chiuso
3 di 6 voci
Task in ritardo
4
Richiedono attenzione
Task Blocked
1
Voci di log aperte: 3
Da seguire
- Task #1 "Kick-off" — in ritardo (fine 2026-09-01)
- Task #2 "Prepare source connection" — in ritardo (fine 2026-09-08)
- Task #3 "Extract and map data" — in ritardo (fine 2026-09-18)
- Task #5 "Prepare validation" — in ritardo (fine 2026-10-02)
- Task #5 "Prepare validation" — Blocked
- CTL-002 "Confirm pilot plants" — scadenza 2026-09-04 superata
Task per Status
Not Started
2
In Progress
2
Completed
2
Blocked
1
On Hold
1
Cancelled
1
Activity Log per Type
Action
1
Decision
1
Risk
1
Dependency
1
Change Request
1
Bug / Defect
1
Avanzamento per Owner
- 1Supplier1/1 completati
- 2Business Owner1/1 completati
- 3Data Team0/2 completati
- 4Delivery Manager0/1 completati
- 5Business + IT0/1 completati
- 6Sponsor0/1 completati
- 7IT + Supplier0/1 completati
- 8Support Team0/1 completati
Prossime scadenze
- 2026-10-14#8 Pilot releaseIT + Supplier
- 2026-10-23#9 HypercareSupport Team